Glenfield Bridge replacement

Latest update

Progress to date

July 2025 – April 2026: Design, planning and procurement

Planning permission was granted on 15 January 2026, with associated planning conditions subsequently discharged on 13 April 2026.

The construction contract was issued to SBC Contracts on 18 February 2026 and formally awarded on 17 March 2026.

February 2026: Advance works

Advance enabling works were undertaken, including the temporary relocation of the tenant at Huddersfield Yard B, additional site investigation works, and tree removal operations.

11 May 2026: Start of main works

Main construction works commenced, including site establishment, implementation of a pedestrian diversion route, and removal of the existing boardwalk and approach ramp. The existing bridge is scheduled for removal by crane in the following phase of works.

Images of works as it progresses can be found on our Flickr site.

Pedestrian diversion

A signed pedestrian diversion route has been established and is currently in operation. A member of the public has raised concerns regarding the absence of dropped kerbs at crossing points along Huddersfield Street.

In response, footway kerb ramps are being procured and will be installed as soon as possible to ensure that accessibility is maintained for all users.