Latest update
Progress to date
July 2025 – April 2026: Design, planning and procurement
Planning permission was granted on 15 January 2026, with associated planning conditions subsequently discharged on 13 April 2026.
The construction contract was issued to SBC Contracts on 18 February 2026 and formally awarded on 17 March 2026.
February 2026: Advance works
Advance enabling works were undertaken, including the temporary relocation of the tenant at Huddersfield Yard B, additional site investigation works, and tree removal operations.
11 May 2026: Start of main works
Main construction works commenced, including site establishment, implementation of a pedestrian diversion route, and removal of the existing boardwalk and approach ramp. The existing bridge is scheduled for removal by crane in the following phase of works.
June 2026
Good progress has been made on site in recent weeks, including:
- The existing bridge has been successfully removed using a crane, and the associated abutments have now been demolished.
- The foul water diversion works on the south side have been completed, including the construction of four new chambers.
- On the north side, the abutment and adjacent footpath have also been demolished.
- The new bridge structure has been fabricated.
Works are currently paused on the north side while technical approval is awaited from Scottish Water for the proposed water main diversion. This diversion will be undertaken in two phases:
- Temporary phase - the pipe will be moved laterally to allow excavation works for the new abutment to proceed.
- Permanent phase - once construction is complete, the pipe will be relocated to align with the new footpath.
Images of works as it progresses can be found on our Flickr site.
Pedestrian diversion
A signed pedestrian diversion route has been established and is currently in operation. Ramps are in place to maintain accessible access for all.