- Title or Description
- Care Villages
- FOI Number
- 2024507
- Date Received
- 14/05/2024
- Type of Request
- FOI
- Request or Question
- Please add me to any updates on progress on the proposed care villages in Tweedbank and Hawick. What is the timescale for completion? What is the anticipated cost? Also, can you confirm what the net gain in beds will be at Tweedbank, taking into account the closure of Garden View and Waverley?
- Response
- Estimated completion is the end of 2026. Hawick Requirements still being developed so currently no timescale for completion. Tweedbank Anticipated cost is 19.3 Million. Hawick Requirements still being developed so currently no anticipated cost is available. Net gain in beds at Tweedbank will be 11 (Eleven).