Easter Langlee - landfill and waste transfer station

Latest news

April 2017

Our Planning Committee voted 5-2 to refuse the application for a waste transfer station at Easter Langlee due to concerns with the C77 access road.

We will now consider its options ahead of the 2021 ban on waste going to landfill.

January 2017

Easter Langlee Waste Transfer Station

Following the successful Public Exhibition held in September 2016, the project team have being working over the subsequent months to develop the plans and proposal taking into account all feedback received from members of the public and other statutory consultees during our pre-application consultation.

We are pleased to confirm that progress to close the landfill has reached another significant millstone with the submission of our Full Planning Application for the proposed new Easter Langlee Waste Transfer Station.

To view our proposed Waste Transfer Station Planning Application and supporting documentation please follow the attached link:

Planning Reference 16/01417/FUL: Waste Transfer Station Planning Application

The full planning application was submitted in January 2017 and is now in the consultation phase. If you wish to make comments of objection or support for our planning application while it is open for consultation please do so by either of the following.

To comment online you must register on the public access portal. It only takes a couple of minutes and will also allow you to track applications and save searches.

Once registered, please follow the steps below:

  1. Log in to your account Select 'Search>Planning>Simple search' and find the application you wish to comment on
  2. On the right side of the page select 'Make a public comment'
  3. Enter your comments
  4. Select 'Submit'

    To comment by post, please write to the following address and include the following:

  • the date
  • the name and address of the sender
  • the reference number of the application
  • the address of the site
  • your comments

    Planning and Regulatory Services
    Scottish Borders Council Headquarters
    Newtown St. Boswells
    Melrose
    TD6 0SA

    Any comments you submit will be published, along with your name, and will be available for inspection and to be copied by any interested party.

We have completed the latest phase of capping on the landfill.  The capped area has increased our gas extraction on the site and the additional wells were connected up to the gas collection network in December.  If you visit the recycling centre you will pass the recently capped area on your left, just as you approach the recycling centre.  We are working to relocate the fence to the top of the newly capped area, and once we have done this we will install the odour control unit at the higher level, to maximise its impact.

September 2016

Plans for a Waste Transfer Station at Easter Langlee near Galashiels will go on display to the public on Thursday 29 September.  The proposed design of the facility will be available to view from 3pm to 8pm in the Blue Room at Langlee Community Centre, with members of the public able to provide feedback and ask any questions about the project.  The consultation event is part of the pre-planning notification process for the waste transfer station, which is required before a planning application for any large development can be made.

Councillors decided in August last year to close Easter Langlee landfill site when it reached its capacity, which is expected to happen in 2018.  The Council has since been developing plans for a new waste transfer station at the same site. This will enable onward transfer of waste for treatment once the landfill is closed.

SBC’s Executive Member for Roads and Infrastructure, Councillor Gordon Edgar, said: “The plans for a waste transfer station are important due to changing legislation which led to the Council deciding to close the landfill site at Easter Langlee.  The project team has already met with resident groups close to Easter Langlee but we would encourage members of the public to come along to this consultation event to see the plans and ask Council officers any questions they may have about the project.  After the public exhibition, the aim is for the full planning application to be submitted next month, and if approved the waste transfer station is expected to open in 2018.”

August 2016

Over the last few months we have been working to deliver the next phase of capping.  We are going to cap along the southern edge of the site – the section that runs along the edge of the access road to the community recycling centre.  Our contractors are scheduled to start the works at the end of August and if all goes to plan they will take approximately 6 weeks to cap the planned area.  If weather conditions are difficult this could take longer.  Once the cap has been installed our gas contractors will install additional gas wells and connect these to the site’s pre-existing gas collection system.

June 2016

We are progressing with works to close the landfill and we have submitted the pre-application notification for the proposed new Easter Langlee Waste Transfer Station. This is the first stage of developing the planning application which we plan to submit in late August/early September. Further information on this stage of the planning process for major developments is available.

View our proposed waste transfer station pre-application.

The pre-application notification covers information on the consultation that is planned. This consultation will include meeting with local community councils and local resident representatives, and holding a public exhibition. During these events we will be sharing the designs of the facility and there will be opportunity for feedback to be given prior to the formal application being submitted.

April 2016

We have started using the new haul road which is enabling us to get up to the higher levels of the landfill and work towards the next stage of capping.  We are currently reviewing tonnage inputs and site profiles to determine which areas we can cap next.  We are continuing to operate the odour control unit during operational hours and have a falcon on site 5 days/week.

January 2016

Heavy rainfall meant that we needed to disconnect one of the gas capture lines on the landfill site in order to install extra water pumps within the landfill site.

When rain water dropped to a safe level in the last week of January we immediately reconnected the gas well.

This period of disconnection could have resulted in a small increase in the risk of odour events during this time.

In December we observed an increase in bird numbers at the site. We have therefore increased the days that a falcon is on the site to reduce these numbers.

October 2015

We completed capping an additional area on the western side of the landfill site.

The gas infrastructure in this area was then re-drilled to maximise gas extraction

The amount of gas being extracted from the site has increased since this extra gas infrastructure has been in place, reducing the risk of odour. In addition to the capping works we also constructed a new haul road that vehicles will be able to use to access the upper levels of the landfill site. This will allow us to maximise future capping areas in the site.

August 2015

We decided the landfill site will be closed when it reaches its current capacity. Between now and closure of the landfill which is expected to take place in 2017, a project will take place to build a new waste transfer station at Easter Langlee.

When the landfill site closes, this transfer station will accept the waste that the landfill site used to accept.

This decision was made in the light of changing legislation, and the termination of a contract for a waste treatment facility at Easter Langlee.